Domchanch Urban Water Supply Project, JUIDCO – Water Supply Project

Jharkhand Urban Infrastructure Development Company
Domchanch , Jharkhand
    • Domchanch Urban Water Supply Scheme with 5 Years of Operation & Maintenance
    • 1. Infiltration Well
      • Diameter of Well: 4.80 m
      • Depth of Well: 5.90 m
      • Jack Well cum Pump House
      • Diameter of Jack Well: 6.0 m
    • 2. Raw Water Pumping Machinery (1W + 1S)
      • Discharge: 133.50 LPS
      • Head: 57 m
      • Hours of Operation: 16 Hours
    • 3. Raw Water Main (Intake Well to WTP)
      • Pipe Diameter: 450 mm DI Pipe
    • 4. Water Treatment Plant (Proposed)
      • Capacity: 10 MLD
    • 5. Staff Quarter
    • 6. Clear Water Pumping Machinery (1W + 1S)
      • Discharge: 133.50 LPS
      • Head: 35.00 m
      • Hours of Pumping: 16 Hours
    • 7. Transmission Main (Clear Water Rising Main)
      • Pipe Diameter: 350 mm DI K-9 Pipe
      • Total Length: 4904 m
    • 8. Elevated Service Reservoir (ESR)
      • Proposed ESR: 2 Nos
      • ESR-1: 1950 KL, Staging Height – 29 m
      • ESR-2: 1800 KL, Staging Height – 24 m
      • Existing ESR-3: 170 KL, Staging Height – 21 m (DWSD Campus)
    • 9. Distribution Network
      • 100 mm DI-K7 – 26,952 m
      • 150 mm DI-K7 – 6,733 m
      • 200 mm DI-K7 – 6,004 m
      • 250 mm DI-K7 – 2,787 m
      • 300 mm DI-K7 – 815 m
      • 350 mm DI-K7 – 601 m
      • 400 mm DI-K7 – 1,934 m
      • 450 mm DI-K7 – 43 m
    • 10. House Service Connections
      • Total Connections: 7,161 Nos
    • 11. NH Crossing
      • Total: 2 Nos
    • 12. Railway Crossing
      • Total: 1 No
    • SCADA & Automation